Sample of a Completed Literature Review Project Schedule
Deadline: (fill in the blank with the assignment due date)
Row 1 (titles of columns):
- Column 1: Start Date
- Column 2: End Date
- Column 3: Activity
- Column 4: Complete?
Row 2:
- Column 1, Start Date: Friday, June 12
- Column 2, End Date: blank
- Column 3, Activity: Plan your approach, read the assignment instructions and case study thoroughly
- Column 4, Complete?: check box
Row 3:
- Column 1, Start Date: Monday June, 15
- Column 2, End Date: Tuesday June, 16
- Column 3, Activity: Conduct the research that is needed
- Column 4, Complete?: check box
Row 4:
- Column 1, Start Date: Wednesday, June 17
- Column 2, End Date: Friday, June 19
- Column 3, Activity: Conduct and draft your analysis
- Column 4, Complete?: check box
Row 5:
- Column 1, Start Date: Saturday, June 20
- Column 2, End Date: Sunday, June 21
- Column 3, Activity: Create your alternatives and decision criteria and draft these sections
- Column 4, Complete?: check box
Row 6:
- Column 1, Start Date: Monday, June 22
- Column 2, End Date: Tuesday, June 23
- Column 3, Activity: Draft your recommendation and implementation plan
- Column 4, Complete?: check box
Row 7:
- Column 1, Start Date: Wednesday, June 24
- Column 2, End Date: blank
- Column 3, Activity: Draft your introduction
- Column 4, Complete?: check box
Row 8:
- Column 1, Start Date: Thursday, June 25
- Column 2, End Date: blank
- Column 3, Activity: Draft your conclusion
- Column 4, Complete?: check box
Row 9:
- Column 1, Start Date: Friday, June 26
- Column 2, End Date: blank
- Column 3, Activity: Draft your executive summary
- Column 4, Complete?: check box
Row 10:
- Column 1, Start Date: blank
- Column 2, End Date: Saturday, June 27
- Column 3, Activity: Edit your work for macro and micro writing issues (e.g., Munter & Hamilton, 2014)
- Column 4, Complete?: check box
Row 11:
- Column 1, Start Date: blank
- Column 2, End Date: Saturday, June 27
- Column 3, Activity: Include buffer before the deadline due to potential online submission errors, etc.
- Column 4, Complete?: check box
Row 12:
- Column 1, Start Date: blank
- Column 2, End Date: Sunday, June 28
- Column 3, Activity: Submit final copy
- Column 4, Complete?: check box